Project Overview

GEM Enterprise carried out a detailed structural assessment of The Barge Dock in Kingston upon Thames (originally part of Kingston Power Station) to evaluate current condition and specify make-safe and repair works. The dock had not benefitted from recent inspections or significant maintenance. Our scope focused on structural safety, arresting deterioration, and setting a practical pathway to bring the dock back into reliable use and manageable maintenance.

 

Client:

Private client

Sector:

Marine / Waterfront (private)

Location:

Kingston upon Thames, UK

Date:

August 2023

Our Role:

Condition survey; defect mapping; repair specification; method and environmental considerations; maintenance plan

Key Facts

  • Structure: Historic barge dock (mass concrete and reinforced concrete with timber fendering)
  • Primary defects: Severely decayed fender timbers; spalled concrete exposing reinforcement; widespread biological growth (moss/algae/mould) indicating retained moisture
  • Deliverables: Annotated defect drawings; prioritised repair schedule; outline details for timber replacement and concrete repairs; cleaning methodology; maintenance regime

 

Project Challenges

  1. Severe decay of fendering timbers
  • Finding: Fender strips and sacrificial timbers heavily degraded.
  • Risk: Loss of impact protection for craft and the dock edge; local damage to parent concrete during berthing.
  1. Concrete damage with exposed reinforcement
  • Finding: Areas of spalling and delamination exposing steel.
  • Risk: Ongoing corrosion and section loss; reduced durability and potential for localised failure if left untreated.
  1. Biological growth and moisture retention
  • Finding: Moss, algae and mould across shaded/constantly damp surfaces.
  • Risk: Accelerated deterioration, slippery walking surfaces, and impeded drainage.

 

Our Solutions

1) Timber fendering replacement (immediate priority)

  • Replace decayed members with marine-grade fendering (e.g., sustainably sourced greenheart/oak, or recycled composite fenders where appropriate).
  • Stainless/galvanised fixings; isolation washers to reduce bimetallic risk at steel interfaces; sacrificial rub-boards where frequent contact is expected.
  • Allow for replaceable wear pieces to simplify future maintenance.

2) Concrete repairs to arrest corrosion

  • Break out defective concrete to sound substrate; clean and passivate exposed reinforcement; reinstate with a BS EN 1504 compliant repair system (primer, repair mortar, bonding/curing as specified).
  • For edges/arrises, use fibre-reinforced repair mortars and formwork to restore geometry; re-coat with a protective anti-carbonation finish in splash zones.
  • Where section loss is significant, introduce local stainless anchors/dowels to secure repairs to the parent structure (to BS 8539 principles).

3) Cleaning & biological control

  • Pressure-wash surfaces within agreed pressure limits to avoid substrate damage; apply biocide suitable for aquatic environments.
  • Reinstate/clear drainage paths; consider slip-resistant finishes on access steps/walkways.

4) Method, access and environmental controls

  • Prepare a method statement covering floating plant access or pontoon work, exclusion zones, debris containment and waste handling.
  • Liaise with the local navigation authority (non-tidal Thames) regarding access windows/closures; schedule works to avoid fish-spawning periods and comply with pollution prevention measures (silt curtains, spill kits).
  • Apply permit-to-work controls for over-water operations; ensure rescue provision and life-saving equipment are in place.

 

Outcomes

  • Safety improved: reinstated impact protection and removal of immediate hazards.
  • Durability restored: concrete repairs and protective finishes arrest corrosion and extend service life.
  • Manageable upkeep: a planned maintenance regime (inspection/cleaning intervals; fender wear-piece replacement) reduces future cost and risk.

 

 

Services Provided

Condition survey & defect mapping · Fendering replacement design · Concrete repair specification · Cleaning/biocide methodology · Over-water method & environmental inputs · Maintenance plan & inspection schedule

 

 

Why Choose GEM Enterprise?

Expertise in Complex Structural Challenges

  • Advanced Engineering Solutions: Skilled in addressing intricate structural issues through innovative engineering practices.
  • Innovative Approaches: Utilises cutting-edge technology and methodologies.

 

Customised Solutions

  • Tailored Designs: Solutions crafted to meet the specific needs of each project and client.
  • Client Collaboration: Works closely with clients to understand their requirements and achieve desired outcomes.

 

Commitment to Quality

  • Stringent Quality Control: Maintains high standards throughout project execution, from design to commissioning.
  • Safety Focused: Prioritises safety in all aspects of design and implementation, adhering to the highest industry standards.

 

Get in touch with our experts today.

Ready to start your project?

Own a pier, quay, dock or private dock that needs attention? Book a 15-minute consult to get a practical repair plan and maintenance schedule.